Myanmar starts Yangon circular railway upgrading project
Source: Xinhua   2018-02-23 10:04:01

YANGON, Feb. 23 (Xinhua) -- The state-run Myanmar Railways has begun a project of upgrading the Yangon circular railway with the first section in the western Yangon commuter rail network, the official Global New Light of Myanmar reported Friday.

The western Yangon commuter network runs from Insein to Tanyingone station and the 6-km sectional project, which started on Wednesday, is expected to complete by the end of May.

The second part of the project, which will renovate the 8.8-km railway between Insein and Kyeemyindaing stations, will start on Oct. 1 and is expected to be finished by the end of January 2019.

The third part of the project, which renovates the 4.4-km railway between Kyeemyindaing and Yangon stations, will commence on Feb. 1, 2019 and be completed in March of the year.

The upgrading project, to be carried out under the management of the Ministry of Transport and Communications, will be funded with 206 million U.S. dollars from Japan International Cooperation Agency (JICA) as an overseas development assistance loan and 94.76 million U.S. dollars from the national fund.

The project aims to increase the numbers of passengers and reduce running and waiting hours.

The running hours of the full circuit of the circular train will be reduced by an hour after the upgrading while it currently takes about three hours.

Out of 2.5 million passengers using public transportation, about 90,000 people use railway transport in Yangon region daily.

Editor: Jiaxin
Related News
Xinhuanet

Myanmar starts Yangon circular railway upgrading project

Source: Xinhua 2018-02-23 10:04:01
[Editor: huaxia]

YANGON, Feb. 23 (Xinhua) -- The state-run Myanmar Railways has begun a project of upgrading the Yangon circular railway with the first section in the western Yangon commuter rail network, the official Global New Light of Myanmar reported Friday.

The western Yangon commuter network runs from Insein to Tanyingone station and the 6-km sectional project, which started on Wednesday, is expected to complete by the end of May.

The second part of the project, which will renovate the 8.8-km railway between Insein and Kyeemyindaing stations, will start on Oct. 1 and is expected to be finished by the end of January 2019.

The third part of the project, which renovates the 4.4-km railway between Kyeemyindaing and Yangon stations, will commence on Feb. 1, 2019 and be completed in March of the year.

The upgrading project, to be carried out under the management of the Ministry of Transport and Communications, will be funded with 206 million U.S. dollars from Japan International Cooperation Agency (JICA) as an overseas development assistance loan and 94.76 million U.S. dollars from the national fund.

The project aims to increase the numbers of passengers and reduce running and waiting hours.

The running hours of the full circuit of the circular train will be reduced by an hour after the upgrading while it currently takes about three hours.

Out of 2.5 million passengers using public transportation, about 90,000 people use railway transport in Yangon region daily.